From idea to keys

The six phases of an ADU project

From "thinking about it" to a certificate of occupancy.

Most LA-area projects run 10 to 14 months end-to-end — slower in Pasadena and Santa Monica, faster with a pre-approved standard plan. Here's the sequence, in plain language.

The six phases
  1. 01

    Feasibility & design intent

    Walk the lot. Confirm zoning, setbacks, easements, hillside or coastal overlays. Pick a rough size and ADU type. Often paired with a free architect consult.

    3–6 weeks
  2. 02

    Working drawings

    Architect produces permit-ready plans — site plan, floor plans, elevations, structural notes, MEP schematics. Soils report and survey ordered if the lot requires them.

    4–8 weeks
  3. 03

    Plan check & corrections

    Submit to the city. State law caps the first review at 60 days, but most projects go through two or three rounds of corrections — that's where the real timeline lives.

    6–12 weeks
  4. 04

    Permit issuance & pre-construction

    Pay fees. Pull the permit. Line up the contractor's crew, financing draw schedule, and utility-coordination paperwork.

    1–2 weeks
  5. 05

    Construction

    Site prep, foundation, framing, MEP rough-in, drywall, finishes. Inspections happen at each gate. Detached ADUs typically run 5–8 months; garage conversions run 3–5 months.

    4–8 months
  6. 06

    Final inspection & Certificate of Occupancy

    Final building, electrical, plumbing, and (if applicable) fire inspections. Address punch-list items. Once the C of O is issued, you can legally rent it.

    2–4 weeks

End-to-end: typically 10 to 14 months.

Get started

Start phase one this week.

Open your city's dossier or run the estimator — both are designed to compress phase one into an afternoon.

Get matched with builders → Use the estimator